The Red Circle Drive Turn Lane Improvements project proposes the addition of a turn lane and signal improvements at the intersection of Red Circle Drive and Shady Oak Road. The
improvements accommodate increased development in the Opus area and are consistent with the Opus AUAR Study

See proposed project map

Proposed improvements

Plans and specifications have been prepared in coordination with Doran Development for the construction of an additional turn lane on Red Circle Drive.  The work associated with this project includes a relocation of an existing water main,  storm sewer and modifications to the traffic signal, medians and pedestrian crossing. 

Project schedule

Following council approval, bids for the project would be received in March or April of 2023 and presented to council for final approval in March or April. Construction would begin in the spring of 2023 and is planned for completion in the summer of 2023.

Project updates

Nov. 3, 2023

Next week crews will pave the final layer of asphalt on Red Circle Drive and Shady Oak Road. 

Temporary pavement markings will be installed after paving operations are complete. 