Bren Road Water Tower Reconditioning

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

The City of Minnetonka’s water tower located at Bren Road and Vista Drive, just south of Lone Lake Park, is being reconditioned in 2018-19 to protect water quality and the city’s investment in the tank, and to improve the look of the tower.


April 3, 2019 project update

The final stages of the water tower reconditioning project will take place in April–May. The anticipated timeline is:

  • April 22: Pressure washing begins
  • April 29 – May 4: Draining the tank
  • May 6 – 24: Final painting

The timeline is weather dependent and subject to change.