The City of Minnetonka is proposing street improvements along Wayzata Boulevard between Cheshire Lane and Plymouth Road (CSAH 61). The project includes pavement mill and overlay, damaged curb and gutter and sidewalk replacement, pedestrian ramp upgrades, and utility casting improvements. Construction is planned for 2024.

Project updates

Oct. 25, 2024

Minnetonka Public Works is looking for your feedback regarding the Wayzata Boulevard Improvement Project. Please complete our survey before Nov. 6. Your answers help to improve our communications regarding future infrastructure projects.

Sept. 6, 2024

This week:

  • The final layer of paving was completed
  • Road striping began

Next week:

  • Road striping will be completed
  • Sign installation will begin

Sept. 3, 2024

Construction work on Wayzata Blvd will be taking place overnight on Tuesday, Sept 3. Paving of the final lift of asphalt will occur overnight Tuesday evening into Wednesday morning. Work is taking place overnight to avoid traffic impacts and businesses in the area. This will be the final night of overnight work.

Aug. 23, 2024

This week

  • Restoration began
  • Driveway milling was completed
  • Driveway postponed until next week due to rain

Next week

  • Restoration will continue
  • Driveway paving will begin
  • Final layer of pavement will be added

Aug. 22, 2024

Construction on Wayzata Boulevard will take place overnight tonight, Aug. 22. Asphalt paving of business driveway entrances will occur overnight Thursday evening into Friday morning. Crews have scheduled late night paving to lessen the impacts on business traffic in the area. 

Aug. 8, 2024

Construction on Wayzata Boulevard will be taking place overnight on Thursday, Aug. 8. The first lift of asphalt paving is scheduled to occur overnight Thursday evening into Friday morning. Overnight paving will take place to avoid impacts to traffic and businesses in the area. This is the first of two overnight paving dates, the next of which will happen in a few weeks.

Aug. 2, 2024

This week:

  • Curb and gutter installation was completed
  • Sidewalk installation was completed
  • Concrete driveway installation was completed

Next week

  • Grading in areas where pavement was removed
  • Bituminous patches will be paved
  • Bituminous paving of the base layer will occur

July 29, 2024

Last week:

  • Concrete driveway installation began
  • Concrete curb and gutter installation began
  • Additional driveway removals continued
  • Bituminous trail prepped

 This week:

  • Driveway pavement removal will be completed
  • Concrete driveway installation will be completed
  • Concrete curb and gutter installation will be completed
  • Concrete sidewalk installation will begin
  • If time permits bituminous street patching will begin

July 15, 2024

Last week:

  • Storm sewer installation was completed
  • Curb and gutter removal continued

Next week:

  • Concrete removal will be completed
  • Concrete installation will begin

July 15, 2024

Last week:

  • Roadway milling was completed
  • Sidewalk was removed
  • Bituminous trail was removed

 This week:

  • Storm sewer installation begins
  • Curb and gutter removal begins

July 3, 2024

This week’s activities:

  • Installing erosion control devices
  • Installing traffic control devices
  • Lowering manholes and gate valves in preparation for pavement milling

Next week’s activities:

  • Milling pavement
  • Removing damaged concrete curb and sidewalk

June 18, 2024

Street improvements are expected to begin in July, and will last approximately 6-8 weeks. Detailed information is coming soon. 

The project will include:

  • Pavement mill and overlay
  • Replacement of damaged curb, gutter and sidewalk
  • Pedestrian ramp upgrades
  • Utility cover/inlet improvements.

Aug. 29, 2023

The city hosted a neighborhood meeting. Documents, and the presentation are available below.

Aug. 3, 2023

The City of Minnetonka will host two open house events on Aug. 24 at the Minnetonka Community Center. From 3 - 4 p.m., information will be tailored to Minnetonka businesses, while the 5 - 6 p.m. open house will be tailored to residents.

 


 

Project contacts
Project documents
Neighborhood meeting presentation & documents